How are the Project KPI indicator colors determined?

Overview

In the Project Workspace, the KPI indicators are as follows:

clipboard_e732746c62485aa23ef0e6a81ea8d0774.png

 

Overall: Calculated average

Budget: Forecast vs. Baseline

Schedule: Forecast vs. Baseline

Resource: Forecast vs. Allocated (Green is >95% allocated, Yellow is 70-95%, Red is below 70%)

Scope: Forecasted Effort vs. Baselne (the assumption is made that effort completed equals scope being completed)

Risk:Probability and impact of defined risks

Issue:Volume and impact

Quality: Manual RGY health assessment status set by the project manager