Why isn't the rollup of subproject NPVs to the program equal to the sum of the NPVs?

If  any of the subprojects or the program itself have different cost of capital or discount rates, the rollup to the program may be different from the sum of the component parts.

If the discount rate is the same for all, the rollup will be the sum of the parts.