Rights Required for Baselines and Actuals

Baselines: The administrator must check the Baseline checkbox for the user on the Edit Rights dialog which is opened with the Admin > Edit Rights command. In addition, the user must have project rights (P1 or above) to submit a project baseline; a user must have resource rights (R1 or above) to submit a resource baseline. It is NOT necessary to have data checked out.

Actuals: Labor Actuals can be entered on the Actual Entry sheet in the BFA (Baseline-Forecast-Actual) module. Resource nodes must be checked out to save actuals to the database.