Database-Create Template

Select a project from the drop down list in the dialog. All fields from the current Project Data record are saved in the new template record.

Project phase dates are saved as the number of days from the start of the project.

All skill and resource assignments are saved; non-labor assignments are not saved in the template. If the skill rollup checkbox is checked, resource demand is rolled up into node specific skill demand. Demand with no required skill treated is ignored.

Effort values are stored in the template in relation to the start and end dates of the project. Demand outside the date range of the project start and finish is NOT saved to the template. If effort demand starts n periods after the start of the project, empty initial periods will be present in the template.