Create WBS Structure (Summary and Subtasks)

Subtasks of phases can be entered in a group below the default items and later moved under the appropriate phase with the right click Move Selection command. The alternative is to use the right click Insert Rows command to create empty rows under each phase for the tasks.

Select a set of tasks and milestones below a task that is to be a summary and click the right arrow Indent toolbar icon. The selected task names are indented to the right and the task immediately above them is changed to a summary.

Note: A summary cannot have task assignments. If tasks have been assigned, the Indent command will fail.

A summary is identified by bold highlighting of its row. The dates of a summary are automatically set to the earliest start and latest finish of all its subtasks.

Summaries can be nested to any level.