What minimum rights are needed for a user to be able to create a baseline?

To baseline anything, the user needs the Baseline right (in the administrator's Edit Rights dialog, this is a checkbox). To save a baseline, the user needs P1 rights to the project or P2 or above on the project node, or R1 or higher on the resource node.